Inground Swimming Pool Construction Update

January 6, 2013

Even with the rain this new inground swimming pool construction near Birmingham, AL goes on. Plumbing is complete and tested(first time), tile is in, coping is formed and will be poured 1-8-13. Then the contractor will work for a while. Swimming Pool Services will set equipment, handle electrical to the equipment and when the contractor has completed the structure that will go over this custom inground swimming pool, the plaster will be completed, then startup….we will keep you updated!